Saturday, January 26, 2008

Updated schedule

We're only a month in and already these schedule postings are funny. I look back to estimated schedules only three weeks old and they're nowhere close. Supposedly it gets warmer later in the year, so we'll see if that lets things move along faster.

The tentative schedule is:

Jan 28: Strip forms and waterproof
Jan 31: Backfill
Early Feb: Begin framing / deck
Mid Feb: pour foundation floor