Thursday, January 3, 2008

Schedule changes

The snow from the last two days has delayed things. We're hoping the foundation sub can get started on forming tomorrow when it starts to warm up.

In the meantime, we're getting revised bids on the framing and the plumbing. The changes to the upstairs mean we'll need to get revised bids for most the subs.

The tentative schedule is:

Jan 7-11: Pour footers and walls
Jan 14-18: Finish pour walls and waterproof
Jan 21-25: Rough plumbing and remove forms, backfill
Jan 28-31: Slab work and begin framing / deck