Sunday, June 8, 2008
Brick work done
The exterior is almost complete. The masons finished the brick work and we've got the exterior ready to paint. We should be able to paint this week and basically be done with the outside of the house.




Sunday, May 18, 2008
Saturday, May 17, 2008
Monday, April 7, 2008
Windows In
Sunday, April 6, 2008
Playtime
Thursday, April 3, 2008
Roof is on
Saturday, March 15, 2008
Roof close to finished
Thursday, March 6, 2008
A roof!
Monday, March 3, 2008
Ready for the roof
Sunday, February 17, 2008
Gray Helps Build the House
Saturday, February 16, 2008
Framing updates - 1st floor almost done
Friday, February 8, 2008
Framing update
Saturday, January 26, 2008
Updated schedule
We're only a month in and already these schedule postings are funny. I look back to estimated schedules only three weeks old and they're nowhere close. Supposedly it gets warmer later in the year, so we'll see if that lets things move along faster.
The tentative schedule is:
Jan 28: Strip forms and waterproof
Jan 31: Backfill
Early Feb: Begin framing / deck
Mid Feb: pour foundation floor
The tentative schedule is:
Jan 28: Strip forms and waterproof
Jan 31: Backfill
Early Feb: Begin framing / deck
Mid Feb: pour foundation floor
Friday, January 25, 2008
Walls Poured
Today the second phase of the walls was poured. The pictures below show the walls after they pulled the forms on the first phase of the pour (the basement portion). The 2nd phase - the first floor walls in the bball court - are formed and ready for the pour.