Sunday, August 31, 2008

Upcoming schedule

With the framing, insulation, low voltage, electrical, plumbing and HVAC inspections out of the way, we can hopefully get this project moving again. The next steps are:

The drywall crew starts on Tuesday morning. Here is the schedule of the critical path items for the two months:

Sept 12- Drywall Done
Sept 22 - Painting Done
Sept 22 - Oct 17 - Interior Trim / finish carpentry
Oct 10 - Oct 24 – Flooring