With the framing, insulation, low voltage, electrical, plumbing and HVAC inspections out of the way, we can hopefully get this project moving again. The next steps are:
The drywall crew starts on Tuesday morning. Here is the schedule of the critical path items for the two months:
Sept 12- Drywall Done
Sept 22 - Painting Done
Sept 22 - Oct 17 - Interior Trim / finish carpentry
Oct 10 - Oct 24 – Flooring