Friday, July 6, 2007

Building Permit Attempt #1

We'd been told that New Albany would accept the permit application in two pieces. The site plan and exterior details as one phase, then the detailed internal plans as another phase. When Danielle went to submit the first phase today she was told that they no longer accept things that way. They want the application to be complete.

This is a bit annoying because we need detailed electrical and plumbing plans to submit the full packet. We're still collecting bids for those phases and probably won't have awarded till late next week.

Since the electrical and plumbing subs do those diagrams, that means we're probably two weeks away from being able to submit for the permit.